Dear sir / madam,
For the timeframe(s) mentioned below TenneT requests market parties for extra reserve-capacity with activation time greater than or equal to 5 PTE (block-bids; pay as bid) to solve expected congestion in the area mentioned below, Reserve capacity in Both upward and downward direction area required; please respect the defined power categories.
If necessary after gate closure, you can ask TenneT to supply a request number (phone number is mentioned above).
Date: 10-feb-2012
Period 1
PTE: 29 - 32
Time: 07:00 - 08:00 h
Area: Congestion Management region Zuid-Holland
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 158 MW
Period 2
PTE: 37 - 44
Time: 09:00 - 11:00 h
Area: Congestie Management region / regio Zuid-Holland
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 20 MW
Period 3
PTE: 65 - 68
Time: 16:00 - 17:00 h
Area: Congestie Management region / regio Zuid-Holland
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 166 MW
Period 4
PTE : 69 - 72
Time: 17:00 - 18:00 h
Area: Congestie Management region / regio Zuid-Holland
Desired direction bid: downward / afregelend
Amount extra reserve-capacity: 326 MW
Regards,